STATE CONSTRUCTION COMMITTEE OF THE USSR (Gosstroy USSR)

EniR

unified standards and prices for construction, installation and repair work

Collection E40

MANUFACTURE OF BUILDING STRUCTURES AND PARTS

Issue 4

Parts and assemblies for sanitary systems

Approved by a resolution of the USSR State Construction Committee, the USSR State Committee for Labor and social issues and the Secretariat of the All-Union Central Council of Trade Unions dated December 5, 1986 No. 43/512/29-50 for mandatory use in construction, installation and repair construction work Oh.

Designed for use in construction and installation, repair and construction and similar organizations, as well as in divisions (teams, sections) of production associations, enterprises, organizations and institutions engaged in construction and major renovation economically, transferred to new terms of payment for workers in accordance with the resolution of the Central Committee of the CPSU, the Council of Ministers of the USSR and the All-Union Central Council of Trade Unions “On improving the organization wages and the introduction of new tariff rates and official salaries for workers in production sectors of the national economy.”

Developed by the Central Normative Research Bureau (TsNIB) of the Ministry of Installation and Special Construction Works of the USSR using regulatory materials from other ministries and departments under methodological guidance and with the participation Central Bureau standards for labor in construction (CBNTS) at the All-Union Research and Design Institute of Labor in Construction of the USSR State Construction Committee.

The technology for carrying out the work provided for in the Collection was developed by the State Design Institute “Proektpromventilyatsiya” of the USSR Ministry of Montazhspetsstroy.

Leading performers - V.N. Zolotukhin(TsNIB), G.M.Serebryany(NIS-14 at the Tsentrosantekhmontazh trust).

Performers - A.M. Makarov(NIS-14 at the Tsentrosantekhmontazh trust), M.E. Mikhaleva(TsNIB), A.M. Pyatikopov(GPI “Projectpromventilation”), B.M. Trubitsina, T.S. Voilochnikova(CBNTS).

Responsible for the release is L.N. Kharchenko (CBNTS).

Introductory part

1. The time standards and prices of this issue provide for work on the procurement of components and parts, the preparation of fittings and devices for central heating systems, internal and external heating networks, water supply, gas supply and sewerage, as well as for the equipment of sanitary cabins with pipelines and devices produced by in the workshops of procurement workshops (CPM), equipped with appropriate equipment and devices.

2. In addition to the main work, the time standards of this issue take into account and do not additionally pay (except for specially specified cases): transitions of workers related to the technology of work; carrying and carrying materials, parts, products, instruments and equipment, as well as moving units, parts and other workpieces in containers or “on oneself” at a distance of up to 10 m, and tools and devices within the workshops; cleaning and lubricating machines, tools and equipment and keeping the workplace clean and tidy; preparation and cleaning of tools and accessories; receiving assignments and familiarizing with sketches, drawings and technological maps for the preparation of pipelines; delivery of work.

3. The standards of this issue do not take into account and are paid additionally: machine adjustment; tool sharpening; selection, acquisition, carrying of materials and carrying of products, parts and assemblies to a distance of over 10 m; electric tack, which must be performed by an electric welder or a mechanic with a second profession of electric welder of manual welding.

4. Procurement of pipelines and production of parts and products, as well as preparation of fittings, pumps and instruments are provided in procurement workshops equipped with appropriate equipment and devices. When performing this work directly on the construction site, time standards and prices are multiplied by 1.25 (VCh-1).

5. The diameters of the pipes are indicated by the nominal diameter of the pipes with the following wall thickness:

When processing pipes with walls thicker than the specified N.v. and Rasc. increase for every 1 mm increase in pipe wall thickness:

by 3% (HF-2) in § E40-4-6; E40-4-24; E40-4-37; E40-4-38;

by 6% (HF-3) in § E40-4-2; E40-4-7; E40-4-23.

The standards of this issue provide for the performance of work in accordance with the current Construction Norms and Rules (SNiP).

7. The quality of work must meet the requirements of current technical specifications for production and acceptance of work. Work performed in violation of technical specifications is considered defective.

8. Release time standards provide for the production of work performed in accordance with the requirements of SNiP Sh-4-80 “Safety in Construction”.

9. Tariffing of work was carried out in accordance with the ETKS of Work and Professions of Workers, vol. 3, section “Construction, installation and repair work”, approved on July 17, 1985.

The profession of workers provided for in this issue “Fitters for the manufacture of units and parts of sanitary systems” is called “Fitter” for brevity.

INSTALLATION AND REPAIR CONSTRUCTION WORKS

Collection E40

MANUFACTURE OF BUILDING STRUCTURES AND PARTS

Issue 2

METAL CONSTRUCTIONS

DEVELOPED by the Central Normative Research Bureau (TSNIB) and normative research station No. 1 at the Uralstalkonstruktsiya trust of the USSR Ministry of Motor Construction and Special Construction using normative materials of other ministries and departments under the methodological guidance and with the participation of the Central Bureau of Labor Standards in Construction (CBNTS) at the All-Union Scientific Research Institute and the design institute of labor in construction of the USSR State Construction Committee.

The work production technology provided for in the collection has been agreed upon with the Gorky Design and Technology Bureau (GPTB) of the All-Union Scientific Research and Design Institute Promstalkonstruktsiya.

APPROVED by Decree of the State Construction Committee of the USSR, the State Committee of the USSR on Labor and Social Issues and the Secretariat of the All-Union Central Council of Trade Unions dated December 5, 1986 No. 43/512/29-50 for mandatory use in construction, installation and repair work.

Introductory part

1. The issue contains standards for work on the production of building metal structures and parts in workshops that are on the balance sheet of construction organizations, equipped with appropriate equipment and lifting mechanisms.

2. Production standards provide for the production of structures from rolled, stamped and cold-formed steel profiles in compliance with the quality requirements of the work performed in accordance with SNiP III-18-75 “Metal structures”.

Workers are required to know and comply with all the requirements provided for by the release, regulated by the above SNiP.

Workers are required to know and follow safety rules when performing work in accordance with the requirements of SNiP III-4-80 “Safety in Construction”.

3. The standards are taken into account, except for the cases specified in technical parts and paragraphs of each chapter, the following works:

movement of materials, workpieces and parts within working area(10-15 m);

cleaning metal, parts, semi-finished products from dirt and rust with scrapers and brushes;

familiarization with the drawing and other documentation;

assembly, marking of parts and structures;

turning and turning of parts and assembled structures during processing and assembly;

installation, rearrangement and cleaning of portable ladders and devices within the workplace.

4. The production standards stipulate that all work must be performed by workers of the same profession - a mechanic for assembling metal structures. In this regard, in the composition of the links to the paragraphs of the Collection, the profession of workers is not indicated.

Tariffication was carried out according to the ETKS of works and professions of workers, vol. 2, approved on January 16, 1985.

Chapter 1. Manufacturing of parts Technical part

1. The scope of work given in the paragraphs of the chapter is given in summary indicating only the main operations that characterize the process as a whole. Auxiliary and secondary operations are not mentioned in the scope of work, but their implementation is provided for by the standards and is not paid separately.

Such operations include: sampling of part sizes; turning on and off a mechanism, machine; installation and change of drill, matrix and punch; slinging and unslinging materials, workpieces and parts when moving them by crane; layout of metal and workpieces on racks; feeding parts to the machine; moving and removing parts from the machine; securing parts in the device and detaching them; igniting and maintaining a fire in a forge while bending hot metal.

2. Changing knives on press shears.

3. The processing of different flange angle steel is standardized as the processing of equal flange angle steel according to the average size of the flanges, and when melting and bending steel, the design size is taken according to the wide flange.

UNIFIED STANDARDS AND PRICES FOR CONSTRUCTION,
INSTALLATION AND REPAIR CONSTRUCTION WORKS

Collection E40

MANUFACTURE OF BUILDING STRUCTURES AND PARTS

Issue 3

WOODEN STRUCTURES AND DETAILS

INTRODUCTORY PART

CHAPTER 1. MECHANIZED PROCESSING OF TIMBER TECHNICAL PART

§ E40-3-2. Circular saw with manual feed for longitudinal sawing

§ E40-3-3. Circular saw with mechanical feed for longitudinal sawing

§ E40-3-4. Multi-saw machine with mechanical feed for longitudinal sawing

§ E40-3-5. Circular saw cross-cutting machine

§ E40-3-6. Jointer

§ E40-3-7. Thicknesser

§ E40-3-8. Milling machine

§ E40-3-9. Tenoning machine

§ E40-3-10. Double-sided tenoning machine

§ E40-3-11. Four-sided planer

§ E40-3-12. Drilling and Grooving Machine

§ E40-3-13. Chain mortising machine

§ E40-3-14. Manufacturing of parquet staves on machines

§ E 40-3-15. Processing (grinding) of joinery on a grinding machine

§ E40-3-16. Trimming door leaves on format-edging machines

§ E40-3-17. Material processing with power tools

§ E40-3-18. Sharpening, straightening, setting saw teeth and sharpening knives of woodworking machines and tools

§ E40-3-19. Marking and marking of parts

§ E40-3-20. Rearrangement cutting tools on woodworking machines

Chapter 2. MANUFACTURE AND ASSEMBLY OF ELEMENTS OF BUILDINGS AND STRUCTURES

§ E40-3-21. Manufacturing of trusses and beams

§ E40-3-22. Manufacturing of roof elements

§ E40-3-23. Assembly of window and window filling elements doorways

§ E40-3-24. Manufacturing of gates and carpentry doors

§ E40-3-25. Assembling blind gates from finished parts

§ E40-3-26. Installation of window and door devices

§ E40-3-27. Production of profiled bars and joinery rods

§ E40-3-28. Manufacturing and fitting of mates

§ E40-3-29. Making panels

§ E40-3-30. Manufacturing of scaffolding, stepladders and ladders

§ E40-3-31. Manufacturing of fence elements

§ E40-3-32. Assembling window sill boards from finished parts

§ E40-3-33. Production of carpenter's panels

§ E40-3-34. Production of glued floor panels from bars and slats

§ E40-3-35. Assembly of protective radiator grilles

§ E40-3-36. Manufacturing of small molds for children's playground equipment

§ E40-3-37. Manufacturing of equipment and small items

Chapter 3. ANTISEPTIC AND FIRE PROOF OF WOOD

§ E40-3-38. Preparation of antiseptic and fire retardant compounds

§ E40-3-39. Antiseptic and fire-retardant impregnation of materials

DEVELOPED by the Central Republican Normative Research Station (CRNIS) of Rosagropromstroy under the methodological guidance and with the participation of the Central Bureau of Labor Standards in Construction (CBNTS) at the All-Russian Research Institute of Labor in Construction of the USSR State Construction Committee.

The technology for carrying out the work provided for in the collection has been agreed upon with the Technical Center of Rosagropromstroy.

APPROVED by Decree of the State Construction Committee of the USSR, the State Committee of the USSR on Labor and Social Issues and the Secretariat of the All-Union Central Council of Trade Unions dated December 5, 1986 No. 43/512/29-50 for mandatory use in construction, installation and repair work.

INTRODUCTORY PART

1. The standards of this issue provide for the performance of work in auxiliary production and other facilities included in the balance sheet of construction organizations.

When performing work directly on the construction site N.v. and Rasc. multiply by 1.2 (HF-1).

2. The manufacture of wooden structures and parts by hand, as a rule, is not allowed. This restriction does not apply to construction enterprises that do not have a set of necessary woodworking equipment and manufacture wooden structures and parts in small quantities, i.e. when performing non-serial work.

3. Technical requirements for carpentry and joinery work include:

accuracy of size and shape;

density of mates;

thoroughness of surface treatment;

selection and correct use of wood species, grade and size of materials in accordance with the type and responsibility of the structure.

4. The scope of work in the paragraphs is given indicating only the main operations that characterize the regulated work as a whole.

The standards take into account all auxiliary and preparatory operations that are an integral part technological process standardized work. These include: for chapters 2, 3 - selection of materials, checking the quality of work, adjusting tools during work, moving materials and products over a distance of up to 30 m; for Chapter 1 - testing the operation of machines, lubricating them during operation, rejecting parts, adjusting tools, handing over products, removing chips and dust from machines, eliminating minor faults.

Changing and pointing of cutting tools on woodworking machines, marking and labeling of parts, delivery of parts to the machine, stacking, removal of parts from the machine, removal of waste from the workshop are not taken into account by the standards for processing lumber on woodworking machines and are paid additionally.

5. All paragraphs of this issue provide for materials, structures and products that meet the requirements of current technical specifications and GOSTs in terms of range, quality and condition.

If there are more than three healthy fused knots with a diameter of up to 50 mm or six knots with a diameter of up to 30 mm on 1 m of the treated surface of a timber or board. and Rasc. for manual processing, multiply by 1.2 (HF-2), and for work performed with a power tool - by 1.1 (HF-3).

It is prohibited to apply these coefficients to standards and prices for work on assembly and finishing of products.

6. The standards provide for the manufacture of structures and their parts from soft wood (pine, spruce, fir, aspen, linden, etc.). When using wood of other species N.v. and Rasc. multiply by the coefficients given in the table.

Type of work

Odds

for hard hardwood(oak, ash, hornbeam, beech, etc.)

for medium-hard species (larch, birch, etc.)

Manufacturing of parts and processing of timber using hand or power tools

Processing of lumber on feed machines:

mechanized

Assembly of structures and products with fitting and partial processing of parts

7. When working on woodworking machines, you must follow the special safety instructions.

Maintenance of machines is carried out by workers who have special training and permission to work on woodworking machines.

The machine must be equipped with quickly and reliably operating switching devices for stopping it and, in addition, where possible, with a braking device. The machine must be installed on a solid foundation and plumb.

Transfers to the machine must be securely guarded. If there are several working tools (cutters, etc.) on the machine shaft, then the currently non-working tools must be removed, turned off or tightly closed with cases. The electrical equipment of the machines must be safe and grounded.

Cluttering the approaches to the machines is unacceptable. When using machines, it is necessary to have free areas for laying material and finished products. The machines are equipped with pneumatic suction for sawdust and shavings.

When working with power tools, you must follow following rules safety precautions: light parts must be securely fastened when processing, the power tool must be grounded.

When moving from one place of work to another, regardless of the distance, the motor of the power tool must be turned off, and the current-carrying cable must not be twisted or looped; It is prohibited to lay a cable connecting the tool to the electrical network through access roads and material warehouses; It is strictly forbidden to carry out repairs or corrections to the tool while the motor is running.

CHAPTER 1. MECHANIZED PROCESSING OF TIMBER TECHNICAL PART