home · Appliances · TTK. Carrying out incoming and acceptance inspection of pipe products. The procedure for carrying out construction control during incoming inspection of pipes, shut-off valves, fittings, equipment and materials

TTK. Carrying out incoming and acceptance inspection of pipe products. The procedure for carrying out construction control during incoming inspection of pipes, shut-off valves, fittings, equipment and materials

font size

DESIGN AND CONSTRUCTION OF GAS PIPELINES FROM POLYETHYLENE PIPES WITH A DIAMETER OF UP TO 300 MM - SP 42-101-96 (2019) Current in 2018

9. INPUT INSPECTION OF PIPES AND CONNECTING PARTS

9.1. Each batch of pipes and connecting parts must be accompanied by a document (certificate) from the manufacturer (or a copy certified by the owner of the certificate) confirming their compliance with the requirements of the technical specifications. The certificate must contain the name and trademark of the enterprise, batch number, product designation, batch volume (m, pcs, kg), test results or confirmation of compliance with the requirements of the standard or specifications, batch release date.

There must be markings on the surface of pipes and connecting parts (see clause 3.7).

9.2. When a batch of pipes arrives at construction projects it is necessary to carry out incoming quality control of pipes and connecting parts, the purpose of which is to determine the suitability of a given batch for the construction of gas pipelines. Pipes must be fastened into bags or coils.

9.3. Incoming inspection should consist of determining: the appearance of the surface and the dimensions of pipes and parts. If there are any doubts about the quality of materials received at the construction site polyethylene pipes It is recommended to additionally carry out random testing of samples to determine the value, tensile yield strength and elongation at break. Mechanical tests must be carried out by laboratories of construction and installation organizations or under contracts with testing centers.

9.4. For input control a certain percentage is selected depending on the diameter:

d_e 225 mm - 2% of pipes or connecting parts from the batch

d_e 160 and 110 mm - 1% -"-

d_e 63 and 40 mm - 0.5% -"-

d_e 32 and 20 mm - 0.25% -"-

In any case, the number of pipes must be at least 5 pieces.

When using pipes in coils for incoming inspection, it is necessary to provide a piece of pipe with a length of at least 2 m, sufficient for the production of at least 25 samples.

9.5. In appearance, the pipes must have a smooth outer and inner surface. Minor longitudinal stripes and waviness are allowed, which do not take the wall thickness beyond the limits of permissible deviations (Appendix 6); Bubbles, as well as other individual defects in accordance with GOST 24105 with a depth of more than 0.7 mm, are not allowed on the surface and at the ends of the pipes.

9.6. The internal and external surfaces of the connecting parts must be free of cracks, swelling, burns, cavities, inclusions and other damage. Minor traces from the forming tool are allowed, traces machining and cold joints, protrusions from remote sprues on connecting surfaces are no more than 0.5 mm, and on other surfaces - no more than 3 mm.

9.7. The appearance of the surface of pipes and parts is determined visually without the use of magnifying devices. The depth of defects is determined using a dial indicator with a division value of 0.01 mm.

9.8. The dimensions of pipes and parts (diameters, wall thicknesses) are determined at a temperature of (23±5)°C. Before measurement, the samples are kept at the specified temperature for at least 2 hours.

The outer diameter d_e of pipes is measured on five samples in three sections of each sample at a distance of at least 150 mm from the ends.

The outer diameter of the connecting ends of the parts is measured at each end of at least five parts at a distance of 5 mm from the ends.

For pipes and parts with a diameter of 160 mm or less, the value d_e is determined as the arithmetic mean of measurements of the maximum and minimum diameters in two mutually perpendicular directions in one section. Measurements are carried out with a GOST 166430 caliper or a GOST 7507-78 micrometer of types MT and MK with an error of 0.1 mm.

For pipes and parts with a diameter of more than 160 mm, the d_e value is calculated using the formula:

where: P - perimeter (mm), measured with a GOST 7502-80 tape measure with an error of 0.5 mm;

T is the thickness of the tape measure (mm), measured with a micrometer with an error of 0.01 mm.

9.9. Wall thickness is measured with a wall gauge indicator GOST 11951, or a micrometer type MT GOST 6507-78 with an error of up to 0.01 mm at four points evenly distributed around the circumference:

for pipes - at both ends of each pipe at a distance of 10 mm from the end (at least 5 pipes);

For parts - at each connecting end there are at least five parts at a distance of 5 mm from the end (at least 5 parts).

9.10. The calculated average values ​​of de and each of the wall thickness measurements should not go beyond the permissible deviations regulated by the relevant specifications for pipes and connecting parts.

9.11. Tensile yield strength (delta_rt) and relative elongation at break (E_pp) are determined for pipe material according to GOST 11262-80 on samples from the corresponding number of samples taken according to clause 9.4.

For pipes supplied according to TU 6-19-352-87 and TU 6-49-04719662-120-94, tests are carried out on sample blades of type 1 GOST 11262-80, with a nominal pipe wall thickness of up to 6 mm, and type 2 , with a nominal pipe wall thickness of over 6 mm.

For pipes supplied in accordance with GOST R 50838-95, tests are carried out on sample blades of type 2 GOST 11262-80.

For pipes with an outer diameter of up to 20 mm, tests can be carried out on samples in the form of a pipe section with a length of 160 ± 5 mm. To fix the sample in testing machine clamps of the appropriate shape are used, and plugs 30 mm long made of elastic material (for example, rubber) are inserted into the sample at both ends to avoid crushing.

The thickness of the sample blade is assumed to be equal to the thickness of the pipe wall (without eliminating the curvature of the surface).

To produce sample blades, nozzles 160+5 mm long are cut from pipes selected for testing, from which samples are cut out with a punch or by mechanical processing (milling) so that their longitudinal axis is parallel to the generatrix of the pipe. When the pipe wall thickness is more than 10 mm, blade samples are produced only by mechanical processing.

Tests are carried out at a temperature of 23±2°C on tensile testing machines, for example, types 2054-R5, 2099-R5, IR5047-50 and others, which provide load measurement with an error of no more than 1% of the measured value.

The speed of movement of the clamps and tensile testing machine when testing pipes supplied according to TU 6-19-352-87 is 50±5.0 mm/min for samples with nominal thickness walls less than 6 mm and 25±2.0 mm/min – for samples with a nominal wall thickness of 6 mm or more.

For pipes supplied in accordance with GOST R 50838-95 and TU 6-49-04719662-120-94, the speed is 100±10.0 mm/min for samples with a nominal wall thickness of up to 10 mm and 25±2.0 mm/ min for samples with a nominal wall thickness of 10 mm or more.

9.12. The test result should be taken as follows:

the arithmetic mean value of the yield strength and the minimum value of relative elongation - for pipes supplied according to TU 6-19-352-87;

The minimum values ​​of the yield strength and relative elongation are for pipes supplied in accordance with GOST R 50838-95 and TU 6-49-04719662-120-94.

The tensile yield strength must be no less than 15 MPa (152 kgf/cm2) for pipes made of PE 80 (PSP) according to TU 6-49-04719662-120-94 and no less than 19 MPa (193 kgf/cm2) for pipes made of PE 63 (HDPE) according to TU 6-19-352-87. The relative elongation for the specified pipe materials must be at least 350%.

9.13. If unsatisfactory results are obtained for at least one of the indicators (appearance, size and mechanical properties) this indicator is monitored again on a double number of samples taken from the same batch. In case of repeated unsatisfactory results, control tests are carried out in the presence of a representative of the manufacturer of the given batch of pipes (parts).

9.14. Based on the results of the incoming inspection, a protocol is drawn up (the recommended form of the protocol is given in Appendix 16), which is part of the documentation presented to the acceptance committee when putting the facility into operation.

9.15. If expired guarantee period storage of pipes or connecting parts specified in the technical specifications, then a conclusion on the suitability of pipes or connecting parts for the construction of gas pipelines can be issued either by the manufacturer or by a testing laboratory accredited by the Gosstandart authorities of Russia, after conducting a set of tests regulated by the technical specifications for pipes or details.

9.16. Incoming inspection of pipes and connecting parts supplied abroad is also carried out according to clause 9.4, taking into account the requirements of the technical conditions for delivery.

When organizing pipelines, bends, technological piping, pumping and water supply stations, main gas pipelines etc., required incoming inspection of pipe products.

To carry out control, a technological map is drawn up.

The technological map contains the name of the organization, facility, and instruments used to measure parameters during acceptance. During incoming inspection, pipes and parts welded to them are checked for compliance with the design, technical standards and contractual obligations.

At exhibitions you can see stands with a description of the design of incoming control.

Technological map of incoming inspection of pipe products

A technological map is a standard document, but the detailing is not limited to special requirements; for each object it can be different as needed. The report is provided to foremen, contractors, and technical supervision.

The technological map for incoming inspection of pipe products includes the following types works:

  • checking the accompanying documentation of pipe products,

  • visual inspection of the quality and completeness of the package,

  • checking compliance with storage standards.

The main purpose of incoming control is to prevent the launch of a facility using low-quality products. It is also important to obtain reliable data for assessment real quality in order to compare the expected result with the actual one. Control methods are determined by GOST.

At the incoming inspection, the presence of a quality control inspection is checked. Testing is also part of the process.

Before the start of incoming inspection, an action plan is approved, which, as a rule, includes 2 stages:

  1. Performed visually at the time of unloading quality characteristics and by counting on a quantitative basis.
  2. Control using tools, which you can familiarize yourself with at our exhibition.

Incoming inspection is carried out by checking all accompanying documentation about the product, compliance with the technical standards of the finished product of its individual parts and materials. The severity of control is determined by the construction manager of the facility.

In addition to visual control, counting and measuring parameters, you will need to design necessary documentation and compliance with labor safety rules and regulations in order to consider the inspection completely completed.

Visual inspection is carried out outside the product. Usually they look for the presence of metal breaks, cracks, bookmarks, clamps, dents, thinning, thickening, pores, delamination, fistulas, unwelded seams, waviness, deep scratches, stripping, displacement, presence protective film etc.

This procedure is carried out for each batch of products upon acceptance and delivery. In this case, the batch must consist of products of the same size and identical properties.

Products must have similar temperature treatment characteristics. Each party must have its own passport.

By special agreement of suppliers and receivers of products, documents containing data on additional checks, studies, measurements, samples, etc. may be attached to the passport.

Passport of pipe products

The passport of a batch of products or one product must contain the following data:

  • product name,

  • product or batch number,

  • symbols,

  • number and date of technical specifications or state standard, which were used to produce tubular products,

  • name of the manufacturer's company and its legal address,

  • notes on the properties of the metal used in production,

  • pressure that the product can withstand, guaranteed by the manufacturer and specifications,

  • number of products in one batch,

  • the mass of the entire batch (in kg), and the mass of one product.

The annex to the passport must indicate the characteristics of the material from which the products are made: steel thickness, symbols, number and date of additional and main tests, name of the manufacturing company and its address.

Additionally, the passport may indicate: bending angles of products, diameter, type of metal, grades, customer data, chemical composition. Also, the passport may be accompanied by documents confirming the material data specified in the passport or copies thereof provided by the supplier.

They may indicate the strength class, category, special parameters, conditions, etc. Products and documents may indicate trademark supplier, if deliveries are not made directly from the manufacturer.

Read our other articles.

Technical task

for quality control of pipe products.

1. General provisions.

1.1. The purpose of the inspection is to ensure the manufacture and delivery of pipe products in strict accordance with the requirements " Guidelines on the quality of pipe products, design and construction of the Company's field pipelines in order to ensure their integrity "M-01.06.06-05 oil", standards, specifications and other documents specified in the purchase order.

1.2. The inspection is carried out by contractor, meeting the requirements of clause 7.8. "Guidelines for the quality of pipe products, design and construction of the Company's field pipelines in order to ensure their integrity" M-01.06.06-05 oil"

1.3. The organization performing the inspection must send to the enterprises personnel who have the necessary level of training and experience in accepting pipe products. The inspector must know technical requirements to the quality of pipes.

1.4. When conducting an inspection, inspectors should be guided by:

Requirements of the contract for the supply of products;

Requirements of standards for pigment materials;

Requirements of standards for manufactured products;

Requirements of testing methods and standards in force at the manufacturer;

Requirements of the current rules for the transportation of goods by rail.

Manufacturer's management and quality control system;

The existing system for loading pipe products into railway cars to eliminate the possibility of damage to pipes and jamming of bevels during transportation.

3.2.2 Develop, together with the manufacturer, and approve the following documentation with the Customer:

- Regulations for inspection control– a document defining the functions and responsibilities of the inspection, the procedure for organizing interaction between the inspection and the services of the manufacturer when carrying out inspection control of pipes and the scope of control at each point of the technological chain, as well as the procedure for sampling for incoming inspection, acceptance tests and control tests of pipe products;

Production process specification (MPS) is a document containing a description of the technological routes used in the manufacture of pipe products and the corresponding methods and control points. The manufacturing process specification must include, as a minimum, the following information:

Delivery and incoming inspection of rolled products/workpieces

Steel production process.

Target steel chemical composition and permissible range of variation

Steel casting method

Pipe production method (rolling, welding)

Way heat treatment pipes

Technological control methods and points

Hydrostatic test

Non-destructive testing of pipes

Methods and scope of acceptance tests.

Acceptance Criteria

Labeling and packaging

Traceability

- Standard Production and Inspection Plan (SIP)– a document regulating the inspected characteristics and acceptance criteria in each technological and control operation, as well as the actions of the inspector in case of technology violations or other inconsistencies.

3.2.3 At the Customer’s request, develop, coordinate with the manufacturer and approve the following documentation from the Customer:

- Extended testing program for the first day of production - a document regulating the procedure for extended tests performed at the beginning of production of inspected orders. The purpose of extensive testing on the first day of production is to ensure that the requirements regulatory documentation specified in the supply contract can be fully implemented using the technological route proposed by the manufacturer. Extended tests on the first day of production should include the determination of all characteristics provided for by regulatory documentation (GOST, TU) for pipe products on an increased sample of pipes. In addition, extended testing may include a number of additional requirements.

3.2.4 At the Customer’s request, conduct an inspection of extended tests on the first day of production in accordance with the developed program. In case of obtaining results that do not satisfy the regulatory documentation specified in the supply contract, inform the “Customer”.

4. Preparation for inspection of the next order.

4.1 The inspecting organization must be notified by the “Customer”. about the quantity, type - size, manufacturer of pipe products in accordance with the signed specification.

4.2 After receiving the notification but before starting to execute the order, specialists of the inspecting organization must study:

Regulatory and technical documentation related to the production of this order;

Technological instructions and technological maps and other regulatory and technical documents of the manufacturer related to this order;

4.3 If necessary, adjustments are made to the standard PPI and SPP.

5. Inspection control over production.

5.1 The inspection must be carried out around the clock in accordance with the manufacturer’s schedule.

5.2 When manufacturing products, inspectors must carry out the scope of work indicated in Tables 1-6. The scope of work can be adjusted in accordance with the requirements of the contract for the supply of pipe products. The specific scope of work is determined in accordance with the production and inspection plan (PIP)

Table 1 - The scope of work performed during the inspection of steel electric-welded oil and gas pipelines performed by high-frequency welding.

Technological operations

100% control of documentation (ACS data, log),

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

100% control of documentation (assignments for the company, diagrams and automated control system data), presence of the Inspector at least 2 times per shift.

Periodic presence of the Inspector, but at least 2 times per shift

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

20. Sampling for control tests _________________

100% presence during sampling, checking the correct labeling of samples.

23. Pipe storage

24. Loading pipes

25. Registration of certificates

100% verification of the correctness of quality certificates. The final acceptance of pipes with inspection is evidenced by the signature and seal of a representative of the Organization_____________

Table 2 - The scope of work performed during the inspection of steel electric-welded oil and gas pipelines made by submerged arc welding.

Technological operations

Type and frequency (volume) of control

1. Control of certificate data for rental

100% verification of certificates of the rental supplier plant

2. Control of sheet storage

100% check of sheet storage according to orders

3. Control of sheet markings

to the extent provided for by regulatory documentation, but at least 1 time per shift

4. Control of sampling for mechanical tests, chemical analysis and metallographic research of rolled products

100% presence of the Inspector during sampling, checking the correct labeling of samples.

5. Incoming quality control of rolled products

100% verification of protocols. 100% presence in mechanical tests. 100% inspection of metallographic sections.

6. Checking the geometric parameters of rolled sheets

Periodic check of surface quality and geometric parameters of sheets, but at least 1 time per shift

7. Incoming inspection of welding materials

100% verification of incoming inspection protocols for welding materials

8. Control of settings of welding mills

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

9. Automatic unbrakable control weld seam after welding

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

10. Monitoring the repair of identified weld defects

11. Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

12. Preliminary acceptance of pipes

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

13. Pipe calibration

100% control of documentation (ACS data, log), control of the degree of residual deformation, periodic presence of the Inspector, but at least 2 times per shift

14. Hydraulic testing of pipes

Periodic presence of an inspector;

100% inspection of hydraulic test diagrams;

Control of documentation confirming the status of the pressure gauge used.

15. Sampling for acceptance mechanical and periodic corrosion tests, as well as microstructure assessment.

100% presence during sampling, checking the correct labeling of samples.

16. Sampling for control tests in the contractor’s laboratory

100% presence during sampling, checking the correct labeling of samples.

17. Carrying out acceptance mechanical tests and analysis of the microstructure of the base metal and welded joint

100% verification of protocols. 100% inspector presence during mechanical testing. 100% inspection of metallographic sections.

18. Automatic non-destructive testing of the weld after hydraulic tests

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

Calibration only in the presence of an inspector

19. RTK of the welded seam of the end sections of pipes

Calibration only in the presence of an inspector

20. RUZK of the welded seam of the end sections of pipes

100% control of documentation, periodic presence of the Inspector, but at least 2 times per shift

21. Repair of identified weld defects

100% control of documentation (ACS data, log), periodic presence of the Inspector when repairing defective areas of the weld

22. Mechanical processing of ends

On the first pipes after readjusting the machine or replacing the tool holder, but at least 2 times per shift when the work process is steady

23. MLK pipe chamfers

100% control of documentation, periodic presence of the Inspector, but at least 2 times per shift

Calibration only in the presence of an inspector

24. Final acceptance of pipes

100% control of documentation, periodic presence of the Inspector, but at least 3 times per shift

25. Pipe marking

Periodic presence of the Inspector, but at least 2 times per shift

26. Pipe storage

100% inspection of pipe storage according to sizes and orders.

27. Loading pipes

100% inspection of wagons, wagon equipment. Periodic control of loading and tying of pipes in cars, at least 2 times per shift

28. Registration of certificates

Table 3 -Scope of work performed during inspection of hot-deformed steel oil and gas pipelines.

Technological operations

Type and frequency (volume) of control

1. Control of certificate data for the pipe blank

100% verification of certificates of the rental supplier plant

2. Control of pipe stock storage

100% check of float storage of workpieces

3. Control of marking of pipe blanks

to the extent provided for by regulatory documentation, but at least 1 time per shift

4. Control of sampling for incoming inspection of pipe workpieces

100% presence of the Inspector during sampling, checking the correct labeling of samples.

5. Incoming quality control of pipe blanks

100% verification of protocols. 100% inspection of metallographic sections.

6. Control of the fit of the workpiece into the heating furnace

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

7. Control of firmware, rolling, calibration

8. Interim acceptance of pipes

100% control of documentation (ACS data, logs), periodic presence of the Inspector, but at least 2 times per shift

9. Control of heat treatment of pipes

100% control of documentation (assignments for the company, diagrams and automated control system data), presence of the Inspector at least 2 times per shift.

10. Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

11. Quality control of mechanical processing of ends

At least 2 times per shift at a steady work process

12. Hydraulic testing of pipes

Periodic presence of an inspector;

100% inspection of hydraulic test diagrams;

Control of documentation confirming the status of the pressure gauge used.

13. Automatic non-destructive testing

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

Calibration only in the presence of an inspector

14. Manual non-destructive testing of the weld during final acceptance of pipes

100% control of documentation (journal), periodic presence of the Inspector, but at least 2 times per shift

15. Final acceptance of pipes

100% control of documentation (magazine), periodic presence of the Inspector, but at least 3 times per shift

16. Sampling for acceptance mechanical and periodic corrosion tests, as well as microstructure assessment.

100% presence during sampling, checking the correct labeling of samples.

17. Sampling for control tests in the contractor’s laboratory

100% presence during sampling, checking the correct labeling of samples.

18. Carrying out acceptance mechanical tests and analysis of the microstructure of the base metal and welded joint

100% verification of protocols. 100% inspector presence during mechanical testing. 100% inspection of metallographic sections.

19. Pipe storage

100% inspection of pipe storage according to sizes and orders.

20. Loading pipes

100% inspection of wagons, wagon equipment. Periodic control of loading and tying of pipes in cars, at least 2 times per shift

21. Registration of certificates

100% verification of the correctness of quality certificates. The final acceptance of pipes with inspection is evidenced by the signature and seal of the representative _______________

Table 4 -Scope of work performed during coating application control.

Technological operations

Type and frequency (volume) of control

1. Material control

2. Incoming pipe inspection

3. Shot blasting control

4. Coating (according to order requirements), pipe heating

5 Pipe cooling

6. Acceptance tests

7. Periodic testing

8. Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

9 Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

10. Pipe storage

100% inspection of pipe storage according to sizes and orders.

11. Loading pipes

100% inspection of wagons, wagon equipment. Periodic control of loading and tying of pipes in cars, at least 2 times per shift

12. Registration of certificates

100% verification of the correctness of quality certificates. The final acceptance of pipes with inspection is evidenced by the signature and seal of the representative _______________

Table 5 -Scope of work performed during inspection of rolled (strip) production for electric welded pipes.

Technological operations*

Type and frequency (volume) of control

1. Smelting, finishing, after-furnace processing, vacuum degassing

Temperature and chemical metal composition, consumption of deoxidizers, ferroalloys and modifiers, pressure in the degasser, duration of processes. Periodic control. 100% control of documentation

2. Metal casting

Temperature and speed mode of casting, cooling mode, sampling for chemical. compound. Periodic control. 100% control of documentation

3 Anti-flake treatment of slabs

Temperature and duration of anti-floken treatment Periodic control. 100% control of documentation

Slab sizes, chemical sampling. composition, macrostructure, labeling Periodic control. 100% control of documentation

5. Finishing, acceptance and certification of slabs

Chemical compliance composition, surface condition Periodic control 100% documentation control

6. Acceptance and assignment of slabs for rolling

Compliance with order requirements and technological regulations

7. Heating of slabs before rolling

Heating time, temperature by furnace zones, heat separation. Periodic control.

8. Temperature-time parameters of rolling and controlled cooling

Temperature of the beginning and end of deformation by groups of stands, temperature of the beginning and end of cooling, duration of operations Periodic control. 100% control of documentation

Editing modes, rolled geometry Periodic control. 100% control of documentation

10. Heat treatment

Temperature and time parameters of heating and cooling Periodic control. 100% control of documentation

11. Ultrasonic testing

Setting up flaw detectors in the presence of an inspector

Absence of unacceptable defects Periodic control. 100% control of documentation

12. Mechanical tests

Sampling in the presence of an inspector

Mechanical properties, according to normative and technical documentation Constant monitoring of tests. 100% control of documentation

13 Final acceptance

Product compliance with NTD requirements. 100% control

14. Loading

100% inspection of wagons, wagon equipment. Periodic control of loading and tying of pipes in cars, at least 2 times per shift

15. Registration of certificates

100% verification of the correctness of quality certificates. The final acceptance of pipes with inspection is evidenced by the signature and seal of the representative _______________

*The number and order of technological operations and the scope of control may vary depending on the production technology and order requirements.

Table 6 - The scope of work performed during the inspection of steel electric-welded oil and gas pipelines performed by high-frequency welding with coating.

Technological operations

Type and frequency (volume) of control

1. Control of certificate data for rental

100% verification of certificates of the rental supplier plant

2. Control of roll storage

100% check of float storage of rolls

3. Control of roll markings

to the extent provided for by regulatory documentation, but at least 1 time per shift

4. Control of sampling for mechanical tests, chemical analysis and metallographic studies of rolled products

100% presence of the Inspector during sampling, checking the correct labeling of samples.

5. Incoming quality control of rolled products

100% verification of protocols. 100% presence in mechanical tests. 100% inspection of metallographic sections.

6. Checking the geometric parameters of the rental

Periodic checking of the roll geometric parameters log, but at least once per shift

7. Monitoring the settings of the welding installation and welding parameters

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

8. Checking the quality of removal of internal and external burrs

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

9. Automatic non-destructive testing of the weld after welding

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

10. Checking the correct choice of welding modes based on the results of technological bending tests

100% testing in the presence of an inspector 100% checking samples after testing for cracks in the weld

11. Inspection of local heat treatment modes.

100% control of documentation (assignments for the company, diagrams and automated control system data), presence of the Inspector at least 2 times per shift.

12. Inspection of volumetric heat treatment modes.

100% control of documentation (assignments for the company, diagrams and automated control system data), presence of the Inspector at least 2 times per shift.

13. Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

14. Quality control of mechanical processing of ends

On the first pipes after readjusting the machine or replacing the tool holder, but at least 2 times per shift when the work process is steady

15. Hydraulic testing of pipes

Periodic presence of an inspector;

100% inspection of hydraulic test diagrams;

Control of documentation confirming the status of the pressure gauge used.

16. Automatic non-destructive testing of the weld after hydraulic testing

100% control of documentation (ACS data, log), periodic presence of the Inspector, but at least 2 times per shift

Calibration only in the presence of an inspector

17. Manual non-destructive testing of the weld during final acceptance of pipes

100% control of documentation (journal), periodic presence of the Inspector, but at least 2 times per shift

18. Final acceptance of pipes

100% control of documentation (magazine), periodic presence of the Inspector, but at least 3 times per shift

19. Sampling for acceptance mechanical and periodic corrosion tests, as well as microstructure assessment.

100% presence during sampling, checking the correct labeling of samples.

20. Sampling for control tests in _________________

100% presence during sampling, checking the correct labeling of samples.

21. Conducting acceptance tests for flattening

100% inspector presence during testing.

22. Carrying out acceptance mechanical tests and analysis of the microstructure of the base metal and welded joint

100% verification of protocols. 100% inspector presence during mechanical testing. 100% inspection of metallographic sections.

23. Pipe storage

100% inspection of pipe storage according to sizes and orders.

24. Material control

100% verification of certificates, certificate compliance control

25 Incoming pipe inspection

100% compliance verification of certificates.

Control for. correct labelling, geometric parameters, the presence of defects and contamination

26. Shot blasting control

Periodic monitoring, but at least 3 times per change of pipe speed. Monitoring the degree of cleaning, roughness, dust content on the launch tube and at least every hour, 100% control of surface defects

27. Coating (according to order requirements), pipe heating

Monitoring the speed of the pipe, the heating temperature on the starting pipe periodically at least 3 times per shift, the thickness of each coating layer, the total thickness of the coating, the uniformity of coating periodically at least 3 times per shift.

28 Pipe cooling

Monitoring the surface temperature of the pipes after cooling on the launch pipe and at least 2 times per shift.

29. Acceptance tests

Control of the appearance of the coating, dielectric continuity, adhesion to steel, coating thickness, length of pipe ends free from coating, bevel angle of the coating to the pipe body

30. Periodic tests

Periodic frequency monitoring in accordance with the requirements of regulatory and technical documentation, when changing technology or coating materials, at the request of the customer

31. Checking the correct pipe markings

Periodic presence of the Inspector, but at least 2 times per shift

32. Pipe storage

100% inspection of pipe storage according to sizes and orders.

33. Loading pipes

100% inspection of wagons, wagon equipment. Periodic control of loading and tying of pipes in cars, at least 2 times per shift

34. Registration of certificates

100% verification of the correctness of quality certificates. The final acceptance of pipes with inspection is evidenced by the signature and seal of the representative _____________

6. Acceptance of products.

6.1 Acceptance of products by the Inspector is carried out in accordance with the PPI agreed with the plant and approved in in the prescribed manner"Customer" of pipe products.

6.2 If deviations in the technological process from the requirements of regulatory documentation are identified, as well as when deviations in test technology or measurement inaccuracies are identified, the Inspector must demand immediate correction of the comments and schedule re-testing of the accepted products. If necessary, a report is drawn up with the participation of representatives of the workshop quality control department and the workshop management.

6.3 If the deviations specified in clause 6.2 were not eliminated or resolved during the production process, the Inspector issues a notification addressed to the Head of the Quality Control Department for consideration and implementation of actions by the plant in accordance with the standards of the quality management system adopted at the enterprise and notifies "Customer". The shipment of controversial pipe products must be suspended until the “Customer” makes a decision on its further use.

6.4 If, during the acceptance of products, the Inspector identifies imperfections in the technological chain used, test methods or regulatory documentation according to which the order is manufactured, which may have a critical impact on the quality of the product, the “Contractor” must immediately notify the “Customer” about this. .

6.5 The fact of product acceptance is confirmed by the signature and seal of the inspecting organization in each official copy of the quality certificate prepared by the manufacturer.

7. Traceability of products after they have been shipped from the manufacturer

7.1 The “Contractor” must become familiar with the product acceptance system at the “Customer’s” facilities (warehouses, pipe depots, etc.) and with the “Customer’s” oil pipeline pipe traceability system.

7.2 If the “Customer” identifies products that have passed inspection control and are of questionable or inadequate quality, the “Contractor” must immediately send an authorized representative to the “Customer” to establish the reasons for the supply of products of inadequate quality, participate in filing a claim with the manufacturer and/or “ To the performer."

8. Conducting control tests of pipe products at the initiative of the inspection.

8.1. The purpose of the control tests is to assess the compliance of pipe products shipped from the manufacturer with the regulatory documentation specified in the supply contract, taking into account the additional requirements of the “Customer”.

8.2. Control tests are carried out in the laboratory of the Inspectorate or any other independent accredited laboratory in the following cases:

Periodically, at least once a month for each technological chain used at a given manufacturing plant;

At the initiative of the inspection, if the inspection has good reasons. A good reason may be: a change in the technological chain, a change in the supplier of the conversion material, which has a significant impact on the quality of the finished product, the development of a new type of product, during repeated acceptance tests, etc.;

If it is impossible for the plant to carry out periodic corrosion tests provided for by the technical specifications;

At the request of the “Customer”.

8.3. Carrying out control tests must be agreed upon with the “Customer”.

8.4. Samples for control tests are taken at the manufacturer of pipe products and are accompanied by a selection certificate.

8.5. When conducting control tests, acceptance rules, control and testing methods, quality assessment standards specified in the relevant technical specifications or GOST are applied.

8.6. The inspection must notify the manufacturer of the time and place of the control tests. The manufacturer has the right to send its representatives to monitor the progress of control tests.

SIGNATURES OF THE PARTIES:

INPUT CONTROL OF PRODUCTS

BASIC POINTS

GOST 24297-87

PUBLISHING HOUSE OF STANDARDS

Moscow

STATE STANDARD OF THE USSR UNION

Date of introduction 01.01.88

This standard establishes the basic provisions for the organization, conduct and registration of the results of incoming inspection of raw materials, materials, semi-finished products and components (hereinafter referred to as products) used for the development, production, operation and repair of industrial products.

1. GENERAL PROVISIONS

1.12. The decision to tighten, weaken or cancel incoming control is made by the consumer in agreement with the State Acceptance and the customer’s representative office based on the results of incoming control for the previous period or the results of operation (consumption) of the product.

2. ORGANIZATION OF INPUT CONTROL

2.1. Incoming inspection is carried out by the incoming inspection unit, which is part of the technical control service of the enterprise (association).

2.2. The main tasks of incoming control are:

1) checking the availability of accompanying documentation for the products, certifying the quality and completeness of the products;

2) control of compliance of the quality and completeness of products with the requirements of design and regulatory technical documentation and its application in accordance with permit protocols;

3) accumulation of statistical data on the actual level of quality of the resulting products and development on this basis of proposals to improve the quality and, if necessary, revise the requirements of the technical documentation for products;

4) periodic monitoring of compliance with the rules and shelf life of suppliers’ products.

Workplaces and personnel performing entry control must be certified in the prescribed manner.

Measuring instruments and testing equipment used during incoming inspection are selected in accordance with the requirements of the normative and technical documentation for controlled products and GOST 8.002-86. If metrological means and control methods differ from those specified in the technical documentation, then the consumer agrees on the technical characteristics of the means and control methods used with the supplier, State Acceptance and (or) with the customer’s representative office.

To carry out tests, inspections and analyzes related to incoming inspection, products can be transferred to other divisions of the enterprise (laboratories, control and testing stations, etc.).

3. PROCEDURE FOR CONDUCTING INPUT CONTROL

3.1. Products accepted by the quality control department, the customer's representative office, the State acceptance of the supplier enterprise and received with accompanying documentation drawn up in the prescribed manner are allowed for incoming inspection.

3.2. When conducting incoming inspection it is necessary:

1) check the accompanying documents certifying the quality of the products and register the products in the journals for recording the results of incoming inspection ();

2) control the selection of samples or samples by warehouse workers, check the completeness, packaging, labeling, appearance and fill out the sampling or sampling report;

3) carry out quality control of products according to technological process input control or transfer samples or samples for testing (analysis) to the appropriate department.

3.3. The department that received samples or samples for testing (analysis) conducts tests within the established time frame and issues a conclusion to the incoming control department about the compliance of the tested samples or samples with the established requirements.

3.4. Test or analysis results ( physical and mechanical properties, chemical composition, structure, etc.) must be transferred to production along with tested products.

3.5. Products accepted based on the results of incoming inspection must be transferred to production with the appropriate mark in the accounting or accompanying documents.

Marking (stamping) of accepted products is allowed.

3.6. Products received from the supplier before incoming inspection must be stored separately from those accepted and rejected by incoming inspection.

3.7. Products rejected during incoming inspection must be marked “Defective” and sent to a defective isolator.

4. REGISTRATION OF INPUT CONTROL RESULTS

4.1. Based on the results of the incoming inspection, they draw up a conclusion on the product’s compliance with the established requirements and fill out a logbook for recording the results of the incoming inspection.

4.2. In the accompanying documents for the products, a note is made about the incoming inspection and its results, and the products are marked (branded), if this is provided for in the list of products subject to incoming inspection.

4.3. If the product meets the established requirements, the incoming control department makes a decision to transfer it to production.

If non-compliance with the established requirements is detected during the incoming inspection, the products are rejected and returned to the supplier with a complaint.

If you repeatedly receive low-quality products or receive them in large quantities, the consumer reports this to the territorial body of the Prosecutor's Office at the location of the supplier.

4.4. Based on the results of the incoming inspection, the consumer, if necessary, informs the supplier’s ministry, the customer’s representative office and (or) the State Acceptance Authority at the supplier enterprise about the non-compliance of the products with the established requirements, and in the absence of the latter - the territorial body of Gosstandart at the location of the supplier to take measures in accordance with those assigned to them functions ().

4.5. For electrical radio products accepted by the customer's representative office, information is sent to the customer's head institute for these products ().



departmental subordination of the enterprise

INTELLIGENCE

on the supply of raw materials, materials, semi-finished products and components in violation of the requirements of scientific and technical documentation (TU standards) for the period from _______________________ to ___________________

Note. If materials and components are accepted by the State Acceptance Office or the customer’s representative office, this is indicated in the note.

APPENDIX 3

mandatory

Information submission form

INFORMATION DATA

1. DEVELOPED AND INTRODUCED by the USSR State Committee for Standards

DEVELOPERS

M. G. Iofin(topic leader); L. V. Ermilova(topic leader); Y. G. Ostapchuk, Ph.D. tech. sciences; A. A. Bogatyrev, Ph.D. economy sciences; I. I. Chaika, Ph.D. economy sciences; S. G. Atamas; S. A. Afonin; Yu. F. Afanasyeva; K. V. Lebedev, Ph.D. Tech. sciences; Yu. S. Vartanyan, Ph.D. tech. Sci.

2. APPROVED AND ENTERED INTO EFFECT by the Resolution State Committee USSR according to standards dated 06/04/87 No. 1809.

3. INSTEAD GOST 24297-80

4. REFERENCE REGULATIVE AND TECHNICAL DOCUMENTS

5. Reissue. April 1993


SCHEMES OF INPUT AND OPERATIONAL QUALITY CONTROL OF CONSTRUCTION AND INSTALLATION WORKS

INPUT INSPECTION OF STEEL PIPES AND CONNECTING PARTS


LIST OF REGULATIVE DOCUMENTS

GOST 10705-80* Electric-welded steel pipes. Technical conditions.

GOST 10704-91 Electric-welded straight-seam steel pipes. Assortment.

GOST 20295-85 Welded steel pipes for main gas and oil pipelines. Technical conditions.

GOST 10706-76* Electric-welded straight-seam steel pipes. Technical conditions.

GOST 8696-74* Electric-welded steel pipes with a spiral seam general purpose. Technical conditions.

GOST 8731-74* Hot-deformed seamless steel pipes. Technical conditions.

GOST 8732-78* Hot-deformed seamless steel pipes. Assortment.

GOST 8733-74* Cold-deformed and heat-deformed seamless steel pipes. Technical conditions.

GOST 8734-75* Seamless cold-deformed steel pipes. Assortment.

GOST 3262-75* Steel water and gas pipes. Technical conditions.

TU 1104-137300-357-01-96 Steel water and gas pipes.

TU 14-3-943-80 Electric-welded steel pipes.

TU 14-3-190-82 Seamless steel pipes for boiler plants and pipelines.

TU 14-3-1399-95 Electric-welded steel pipes.

TU 14-3r-13-95 Electric-welded straight-seam steel pipes with a diameter from 20 to 159 mm.

TU 1390-002-01297858-96 Steel pipes with an external anti-corrosion coating made of extruded polyethylene (JSC VNIIST, AKH named after K.D. Pamfilov, Moscow, CJSC ISOPIPE, Ryazan).

TU 1390-001-21042669-98 Steel pipes with a diameter of 57530 mm with an outer coating based on extruded polyethylene (Liniya LLP, Moscow).

TU 1390-003-11928001-2001 Steel pipes with an outer two-layer coating based on extruded polyethylene (Druza JSC, Orenburg)

TU 1390-003-01297858-2003 Steel pipes with a diameter of 89-530 mm with an external anti-corrosion coating made of extruded polyethylene (ZAO "ISOPIPE", Ryazan, ZAO VNIIST-TSAPTR, Moscow).

TU 1390-003-01297858-99 Steel pipes with an outer two-layer coating based on extruded polyethylene (Mapik LLC, Moscow).

TU 1390-005-01297858-98 Steel pipes with an outer two-layer protective coating based on extruded polyethylene (JSC VNIIST, AKH named after K.D. Pamfilov. State Unitary Enterprise MOE pipe procurement plant, Moscow).

TU 1394-005-04005951-97 Steel pipes with an outer protective coating of extruded polyethylene with an outer diameter of 572020 mm (SUE "NIIMosstroy", State Unitary Enterprise MOETZK, Moscow).

TU 1394-009-04005951-99 Steel pipes with an outer two- and three-layer protective coating based on extruded polyethylene (JSC VNIIST, State Unitary Enterprise MOETZK, Moscow).

TU 1394-011-04005951-2000 Steel pipes with two- and three-layer outer protective coating based on extruded polypropylene (JSC VNIIST, State Unitary Enterprise MOETZK, Moscow).

TU 1394-016-04005951-2002 Steel pipes electric welded diameter from 57 to 720 mm with an external anti-corrosion polyethylene coating for gas pipelines (VNIIGAZ LLC, State Unitary Enterprise MOE Pipe Procurement Plant, Moscow).

TU 1394-017-04005951-2002 Electric-welded steel pipes with a diameter of 820 to 1420 mm with an external three-layer anti-corrosion polyethylene coating for main gas pipelines (VNIIGAZ LLC, State Unitary Enterprise MOE Pipe Procurement Plant, Moscow).

TU 1394-018-04005951-2002 Steel pipes with external protective epoxy coating(JSC VNIIST, Moscow, State Unitary Enterprise MOE Pipe Manufacturing Plant).

TU 1394-020-04005951-2003 Steel pipes with an outer three-layer and two-layer polyethylene coating for the construction of main oil pipelines (JSC "VNIIST-TSAPTR", Moscow, State Unitary Enterprise MOE Pipe Procurement Plant).

TU 1468-006-01297858-2001 External polyurethane coating for anti-corrosion protection of parts of connecting units and pipeline units with a diameter of 108 to 1420 mm (JSC VNIIST, Moscow, State Unitary Enterprise MOE Pipe Procurement Plant).

TU 1469-002-04834179-2001 Connecting parts and assemblies of pipelines with a diameter from 219 to 1420 mm with external anti-corrosion polyurethane coating(VNIIGAZ LLC, Trubodetal OJSC, Chelyabinsk).

TU 1469-004-04834179-2002 Connecting parts and assemblies of pipelines with a diameter of 325 to 1420 mm with an external anti-corrosion polyurethane coating (JSC VNIIST, Moscow, JSC Trubodetal, Chelyabinsk).

TU 1390-006-01297858-99 Steel pipes with an outer two-layer protective coating based on extruded polyethylene (JSC VNIIST, Moscow).

TU 1390-008-01297858-2002 Pipes and welded pipe sections with a diameter of 114720 mm with an external anti-corrosion coating based on extruded polyethylene (JSC VNIIST, Moscow).

TU 1390-001-00186654-99 Electric-welded straight-seam steel pipes with a diameter of 508-1420 mm with an external protective coating based on extruded polyethylene (JSC "VNIIST", Moscow).

TU 1390-003-00154341-98 Electric-welded and seamless steel pipes with an external two-layer anti-corrosion coating based on extruded polyethylene (JSC VNIIST, Moscow, LLC Uraltransgaz, LLC "Truboplast Enterprise", Yekaterinburg).

TU 1390-004-32256008-2003 Steel pipes with a diameter of 57530 mm with an outer two- and three-layer protective coating based on extruded polyethylene (ZAO VNIIST-TSAPTR, Moscow, LLC "Truboplast Enterprise", Yekaterinburg).

TU 1390-008-00154341-2002 Steel pipes with a diameter of 57530 mm with an external three-layer anti-corrosion coating based on extruded polyethylene (Uraltransgaz LLC, Truboplast Enterprise LLC, Yekaterinburg).

TU 1390-012-00154341-2002 Steel pipes with a diameter of 102530 mm with an internal protective coating based on epoxy powder compositions (Uraltransgaz LLC, Truboplast Enterprise LLC, Yekaterinburg).

TU 1390-001-01284695-2000 Steel pipes with internal epoxy coating "CORON" (JSC "ATZ", Almetyevsk, Tatarstan).

TU 1390-002-01284695-97 Steel pipes with an external anti-corrosion coating based on extruded polyethylene (JSC "ATZ", Almetyevsk, Tatarstan).

TU 1390-003-01284695-2000 Steel pipes with an external anti-corrosion coating based on extruded polyethylene (JSC VNIIST, AKH named after K.D. Pamfilov, Moscow, JSC "ATZ", Almetyevsk, Tatarstan).

TU 1390-011-01284695-2003 Steel pipes with a diameter of 57530 mm with an outer two-layer and three-layer protective coating based on extruded polyethylene (ZAO VNIIST-TSAPTR, Moscow, OAO ATZ, Almetyevsk, Tatarstan).

TU 14-3R-33-2000 Electric-welded steel pipes with a diameter of 530 to 1420 mm with an external three-layer anti-corrosion polyethylene coating for main gas pipelines (VNIIGAZ LLC, Volzhsky Pipe Plant OJSC, Volzhsky, Volgograd region).

TU 14-3R-39-2000 Steel pipes with a two- and three-layer outer protective coating based on extruded polypropylene (JSC VNIIST, Moscow, JSC PA "VTZ", Volzhsky, Volgograd region).

TU 14-3R-49-2003 Seamless and welded steel pipes with a diameter of 102-1420 mm with an external protective coating based on extruded polyethylene (JSC "VNIIST-TSAPTR", Moscow, JSC PA "VTZ").

TU 14-3R-37-2000 Electric-welded straight-seam steel pipes with a diameter from 102 to 1220 mm with an outer coating based on extruded polyethylene (JSC "VMZ", Vyksa, Nizhny Novgorod region).

TU 14-3R-42-2000 Electric-welded steel pipes with a diameter of 102 to 426 mm with an external anti-corrosion polyethylene coating for gas pipelines (VNIIGAZ LLC, VMZ OJSC, Vyksa, Nizhny Novgorod region).

TU 14-3R-43-2000 Electric-welded steel pipes with a diameter of 508 to 1220 mm with an external three-layer anti-corrosion polyethylene coating for main gas pipelines (VNIIGAZ LLC, VMZ JSC, Vyksa, Nizhny Novgorod region).

TU 1469-004-01297858-2002 Cold bending curves of electric-welded steel pipes 530 and 1220 mm with insulating coating (JSC VNIIST, Moscow).

TU 14-3R-36-2000 Electric-welded steel pipes with a diameter of 508 to 1420 mm with an external three-layer anti-corrosion polyethylene coating for main gas pipelines (VNIIGAZ LLC, Chelyabinsk Pipe Rolling Plant OJSC, Chelyabinsk).

TU 14-3R-61-2002 Seamless and welded steel pipes with a diameter of 102-820 mm with an outer two-layer protective coating based on extruded polyethylene (JSC VNIIST, Moscow, JSC ChTPZ, Chelyabinsk, JSC VMZ, .Vyksa, Nizhny Novgorod region).

TU 14-3R-66-2003 Seamless and welded steel pipes with a diameter of 102-1420 mm with an external three-layer protective coating based on extruded polyethylene (JSC VNIIST, Moscow, JSC Chelyabinsk Pipe Rolling Plant, Chelyabinsk).

TU 1381-002-00154341-98 Electric-welded steel pipes with a diameter of 219-1420 mm with an external anti-corrosion polyethylene coating (Kopeysk Pipe Insulation Plant LLC, Kopeysk, Chelyabinsk region).

TU 1381-003-00154341-2000 Electric-welded steel pipes with a diameter of 219-1420 mm with an external three-layer anti-corrosion coating based on extruded polyethylene (Uraltransgaz LLC, Yekaterinburg, KZIT LLC, Kopeisk, Chelyabinsk region).

TU 1381-004-00154341-2000 Electric-welded steel pipes with a diameter of 219-1420 mm with an external two-layer anti-corrosion coating based on extruded polyethylene (Uraltransgaz LLC, Yekaterinburg, KZIT LLC, Kopeisk, Chelyabinsk region).

TU 1381-009-00154341-2002 Electric-welded steel pipes with a diameter of 219-720 mm with an outer protective two-layer coating based on extruded polyethylene (Uraltransgaz LLC, Yekaterinburg, VNIIGAZ LLC, KZIT LLC, Kopeisk, Chelyabinsk region).

TU 1381-010-00154341-2002 Electric-welded steel pipes with a diameter of 530-1420 mm with an external protective three-layer coating based on extruded polyethylene (Uraltransgaz LLC, Yekaterinburg, VNIIGAZ LLC, KZIT LLC, Kopeisk, Chelyabinsk region).

TU 1381-013-00154341-2002 Bent bends with an external protective polyethylene coating (Uraltransgaz LLC, Yekaterinburg, Kopeysk Pipe Insulation Plant LLC, Kopeisk, Chelyabinsk region).

TU 1381-002-00154341-98 Electric-welded steel pipes with a diameter of 530-1420 mm with an external anti-corrosion polyethylene coating (ZAO Uralremstroy, Chelyabinsk).

TU 4859-001-11775856-95 Steel pipes coated with polyethylene adhesive tapes (AKH named after K.D. Pamfilov, Moscow).

TU 1390-013-04001657-98 Pipes with a diameter of 57530 mm with an external combined tape-polyethylene coating (AKH named after K.D. Pamfilov, Moscow).

TU 1390-014-05111644-98 Pipes with a diameter of 57530 mm with an external combined tape-polyethylene coating (AKH named after K.D. Pamfilov, LLC Firm BOOS-M, Moscow, State Unitary Enterprise MO Mosoblgaz, Klinsky Plant pipe insulation, Klin, Moscow region).

TU 1394-017-50172433-2002 Steel pipes with a diameter of 57-530 mm with an outer two-layer coating based on extruded polyethylene (AKH, Klin Pipe Insulation Plant, Klin, Moscow region).

TU 1394-016-04001657-2001 Steel pipes with an outer two-layer coating based on extruded polyethylene (AKH named after K.D. Pamfilov, Moscow, JSC Firm Gazkomplekt, Reutov, Moscow region).

TU 1394-002-47394390-99 Steel pipes with a diameter of 57 to 1220 mm coated with extruded polyethylene (AKH named after K.D. Pamfilov, Moscow, LLC "Indastle", "Klimentina SK", Moscow).

TU 1390-002-70403923-2004 Steel pipes with an outer two-layer coating based on extruded polyethylene (AKH named after K.D. Pamfilov, Moscow, NefteGazKomplekt LLC, Moscow).

TU 1394-016-03005951-2002 Electric-welded steel pipes with a diameter of 57 to 720 mm with an external anti-corrosion polyethylene coating.

TU 1394-001-05111644-96 Steel pipes with a two-layer coating of extruded polyethylene (AKH named after K.D. Pamfilov, JSC "Firm "Janus", Moscow, JSC "PTZ "Priz-NEGAS", Penza) .

TU 2313-008-17213088-2003 External anti-corrosion coating of connecting parts and shut-off valves for the construction of main oil pipelines (ZAO VNIIST-TSAPTR, OAO NEGASPENZAPROM, Penza).

TU 1394-009-17213088-2003 Steel pipes with a diameter of 57 to 1220 mm with an outer coating based on extruded polyethylene for the construction of main oil pipelines (ZAO VNIIST-TSAPTR, Moscow, ZAO PTZ Priz-NEGAS, Penza).

TU 1394-010-17213088-2003 Steel pipes with a diameter of 57 to 1220 mm with an outer coating based on extruded polypropylene for the construction of main oil pipelines (ZAO VNIIST-TSAPTR, Moscow, ZAO PTZ Priz-NEGAS, Penza ).

TU 1394-011-17213088-2003 Steel pipes with a diameter of 508 to 1420 mm with an external three-layer anti-corrosion polyethylene coating for main gas pipelines (VNIIGAZ LLC, PTZ Priz-NEGAS CJSC, Penza).

TU 1394-012-17213088-2003 Steel pipes with a diameter of 57 to 530 mm with an external anti-corrosion polyethylene coating for gas pipelines (VNIIGAZ LLC, Priz-NEGAS CJSC, Penza).

TU 5768-003-01297858-2002 Thermally hydro-insulated steel pipes for oil and gas pipelines (JSC "VNIIST", Moscow, JSC "NEGASPENZAPROM", Penza).

TU 1394-003-02066613-99 Steel pipes with an external polyethylene anti-corrosion coating (Indastle LLC, Moscow).

TU 4859-003-03984155-2000 Steel pipes with external protective bitumen coating(JSC "Insulation Plant", St. Petersburg).

TU 1390-015-03984155-98 Steel pipes with an external combined tape-polyethylene coating (ZAO Izolyatsionny Zavod, St. Petersburg).

TU 1390-021-43826012-2001 Steel pipes with internal and external anti-corrosion coating (Bugulma Mechanical Plant, Bugulma, Tatarstan).

TU 2312-005-27524984-99 Epovin enamel BEP-5297 (internal enamel coating, LLC "Indastle", Moscow).

TU 1390-001-48061320-99 Steel pipes with an external three-layer protective coating based on extruded polyethylene.

TU 1394-040-01297775-2002 Steel pipes, thermally insulated with polyurethane foam, for oil and gas pipelines (JSC SibNIPIgazstroy, Tyumen).

TU 5768-002-01297858-2002 Steel pipes, thermally insulated with polyurethane foam, for oil and gas pipelines (JSC "VNIIST", Moscow).

TU RB 03289805.002-98 Steel pipes with a diameter of 57530 mm with an outer coating based on extruded polyethylene.

TU RB 03289805.001-97 Steel pipes with a diameter of 57530 mm with an external combined tape-polyethylene coating.

TU U 14-8-34-2001 Electric-welded straight-seam steel pipes with a diameter of 530-1420 mm with an external polyethylene anti-corrosion coating (JSC "VNIIST", Moscow).

TU U 13457882.001-2001 Steel pipes coated on the basis of polyethylene with a polymer adhesive (NPP "Ukrtruboizol", Dnepropetrovsk).

TU 14-3-1954-94 Electric-welded straight-seam steel pipes with a diameter of 1220 and 1420 mm with an external polyethylene anti-corrosion coating (VNIIGAZ LLC, Khartsyzsk Pipe Plant OJSC, Donetsk region).

GOST 8944-75* Connecting parts made of malleable cast iron with cylindrical threads for pipelines. Technical requirements.

GOST 8946-75* GOST 8957-75*, GOST 8959-75*, GOST 8963-75* Ductile iron connecting parts with cylindrical threads for pipelines. Basic dimensions.

GOST 8965-75 Steel connecting parts with cylindrical threads for pipelines Р 1.6 MPa. Technical conditions.

GOST 8966-75, GOST 8968-75, GOST 8969-75 Straight couplings, locknuts and steel bends with cylindrical threads for pipelines Р 1.6 MPa (main dimensions).

GOST 17380-2001 Seamless welded pipeline parts made of carbon and low-alloy steel. General technical conditions.

GOST 17375-2001, GOST 17376-2001, GOST 17378-2001, GOST 17379-2001 Seamless welded pipeline parts made of carbon and low-alloy steel. Steeply curved bends 3D type (R1.5DN). Tees. Transitions. Eleptic plugs. Design.

GOST 24950-81 Bent bends and curved inserts for bends of steel linear parts main pipelines. Technical conditions.

State standards and technical specifications for other materials and technical products provided for by the project.

SNiP 3.01.01-85* Organization of construction production.

SNiP 42-01-2002 Gas distribution systems.

SP 42-101-2003 General provisions for the design and construction of gas distribution systems made of metal and polyethylene pipes.

SP 42-103-2003 Design and construction of gas pipelines from polyethylene pipes and reconstruction of worn-out gas pipelines.

SP 42-102 (project) Design and construction of gas pipelines from metal pipes.

PB 12-529-2003 Safety rules for gas distribution and gas consumption systems.

Instructions for warehousing and storage of pipes with an external factory polyethylene coating, JSC "VNIIST", Moscow, 2002.